Modular Apartments:
Zoning, Code and Approvals
A factory-built apartment building goes through the same zoning and Building Code as any other, with one difference: the factory work is certified in the factory. Here is the approval path from a triplex to six storeys, and what changes as the building grows.
Rules checked · drawn from Ontario, CMHC and CSA published material
What Changes as You Scale
The number of units and the size of the building decide which planning approvals you need and which part of the Building Code governs the design.
| Project | Zoning | Planning approvals | Building Code |
|---|---|---|---|
| Up to 3 units on a serviced urban lot | As-of-right: 3 in the main building, or 2 plus 1 in an ancillary building | No site plan control; additional units are exempt from development charges and parkland charges | Part 9 |
| 4 to 10 units | A fourth unit needs municipal permission; some cities, such as Toronto, allow four as-of-right | Exempt from site plan control at 10 units or fewer, with some exceptions such as land near shorelines or rail | Part 9 up to 3 storeys and 600 m²; Part 3 above |
| 11+ units, low-rise | Rezoning or minor variance where the zoning does not already permit it | Site plan control applies | Part 3: designed and reviewed by architects and engineers |
| Mid-rise to 6 storeys | Rezoning where required | Site plan control applies | Part 3; sprinklered wood-frame construction is permitted up to 6 storeys |
There is no province-wide four-unit rule in Ontario. Rental units get development-charge discounts at every scale, covered below.
How Factory Work Gets Approved
The Building Code accepts factory-built buildings certified to CSA A277, the national procedure for certifying prefabricated buildings, modules and panels. It changes what is inspected where, not which rules apply.
- A certification procedure, not a building code: an independent certification agency audits the factory’s quality program and makes unannounced inspections of its products
- The building still has to meet the Ontario Building Code
- In Ontario, accredited certification bodies include CSA, Intertek and the Quality Auditing Institute
- A building permit covers both the units and the site work
- Concealed work in certified units generally does not need re-inspection on site
- Inspectors still check the foundation, how the units are anchored to it and to each other, the grading, and the electrical and plumbing connections before occupancy
- Volumetric modules arrive as finished rooms and are craned onto a site-poured foundation
- Panelized framing arrives as wall, floor and roof panels manufactured to your drawings and closed in on site
- Panels suit larger and multi-storey buildings where the architect’s own design leads
- Sprinklered wood-frame residential construction is permitted up to 6 storeys
- Encapsulated mass timber is permitted up to 18 storeys since January 1, 2025
- Ontario’s code is now the 2024 Building Code, built on the National Building Code of Canada 2020 with Ontario amendments
Approvals That Got Lighter
Ontario has cut several steps out of the approval path for small and rental projects since 2022, and more changes passed in 2026.
- Residential projects of 10 units or fewer are exempt from site plan control
- Since June 2026, municipalities cannot impose enhanced design standards, such as ornamental or landscaping requirements, beyond health and safety
- A further site plan reform was consulted on in spring 2026; it is a proposal until enacted
- Additional residential units are exempt from development charges and parkland charges
- Purpose-built rental units get a discount of 25% for three or more bedrooms, 20% for two and 15% for others
- Affordable units are exempt, and a federal-provincial program is paying municipalities that cut charges by 30% to 50% or more
- CMHC’s Housing Design Catalogue offers about 50 standardised designs, including fourplexes and sixplexes adapted for Ontario
- The designs are compatible with prefabricated methods such as panelized walls
- Build Canada Homes gives priority to modern methods of construction, including modular and panelized
- At least 15% of suites in an apartment building need basic barrier-free features: a barrier-free path into the kitchen, a bedroom, the living room and a full bathroom
- Houses and buildings under Part 9 are not affected by most accessibility requirements
- Ontario has not adopted the national tiered energy code; housing uses SB-12 and larger buildings SB-10
What Goes Into Your Permit Set
EpicMod is the manufacturer. The units or panels, the drawings and the warranty come from the factory; the site work, foundations and Part 3 design responsibilities stay with your own consultants and contractors.
- For volumetric units, the engineering drawing set: architectural and structural for an exterior-finished shell, plus mechanical and electrical and CSA A277 certification for fully finished units
- For panelized framing, wall, floor and roof panels manufactured to the drawings you supply, from townhomes and multiplexes to mid-rise up to six storeys
- A delivery schedule your lender can test for realism, with units or panels built indoors while site work proceeds
- Pricing fixed at contract, with the exclusions listed in full
- GST/HST, transportation and crane
- Site clearing and servicing, foundations, utility connections, and permit or approval fees
- Interior finishing on an exterior-finished shell. Site work is the property owner’s responsibility, handled by your own trades or your dealer’s crew
- Volumetric units come through the EpicMod dealer for your area; projects of 10 or more units can be supplied directly by EpicMod, at EpicMod’s discretion
- Panelized framing runs through a dealer from 10,000 sq ft per project up to 100,000 sq ft a year, and direct from EpicMod above that
- Compare the two product lines
Modular Apartment FAQ
A Written Quote Against Your Drawings
Send the drawings or the unit mix, the storey count and the site. You get pricing for units or panels, the exclusions in full and a delivery schedule your lender and consultants can work from.
Rules and amounts are drawn from each government body’s published material on the date shown. Programs and regulations change. Confirm with the administering body, your municipality and your own accountant or lawyer before making a decision. EpicMod does not provide tax, legal or planning advice.